CONTROL SYSTEM FOR POWER LINES


About Technology

The goal of the secondary voltage regulation in switching stations is to hold desired voltage (400kV, 220kV) on all bus-bars of the switching station and to hold the flow of wattles current through transformer. The importance of these requirements grew up in the Czech Republic recently in connection with interconnection of the Czech electrification system with the European system UCPTE (Union pour la Co-ordination de la Production et du Transport de l´Electricité).

Voltage and wattles current control is carried out either by changing generator excitation in power stations that feed the switching station or by switching transformer taps in the switching station.

General Information

Number of Controlling Power Stations 3
Type of configuration Hierarchical
Number of levels 3 levels
Type of connection Star
Number of RTUs 5
Max. distance 20 km

Level1 - Central Control Room

Multiuser SCADA System IGSS
Communication with Level 2 HDLC, RS232

Level 2 - Data Concentrator

Number of Stations 1
Communication with Level 3 HDLC, modem

Level 3 - Telemetric Stations ( 1 in each Power Station)

Number of Stations 3
Direct connection with Local actuators/sensors

Total Number of Signals

DI 140
DO 80
AI 80